Time Calculator

Hours worked = end time − start time − unpaid breaks. 07:00 to 15:30 is 8 h 30 min on site; less a 30-minute break that is 8 h a day, or 40 h over 5 days. For payroll, divide minutes by 60 to get decimal hours: 7 h 45 min = 7.75 h. A shift that ends past midnight adds 24 hours to the end time.

Inputs

Results update as you type.

Calculate
Times
Working time on a 24-hour clock8 h 00 min paid a day00:0006:0012:0018:0024:00myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Total for 5 days
40 h 00 min
Total in decimal hours40.00 h
Paid hours per day8 h 00 min
Per day in decimal hours8.00 h
Start to finish per day8 h 30 min
Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Start to finish = 15:30 − 07:00 = 8 h 30 min = 510 min
  2. Paid per day = 510 − 30 min break = 480 min = 8 h 00 min (8:00)
  3. Decimal hours = 480 ÷ 60 = 8.00 h (for timesheets and payroll)
  4. Total = 8 h 00 min × 5 = 40 h 00 min = 40.00 h

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formula

Hours worked = end time − start time − unpaid breaks
If the end is earlier than the start, add 24 h (night shift)
Decimal hours = hours + minutes ÷ 60
Finish time = start time + duration (take off 24 h for each day passed)

Worked Example

A crew works 07:00 to 15:30 with a 30-minute unpaid lunch, 5 days:

  1. Start to finish = 15:30 − 07:00 = 8 h 30 min = 510 min
  2. Paid per day = 510 − 30 = 480 min = 8 h (8.00 decimal hours)
  3. Week = 8 h × 5 = 40 h

Minutes to Decimal Hours

Minutes Decimal hours Minutes Decimal hours
5 0.08 35 0.58
10 0.17 40 0.67
15 0.25 45 0.75
20 0.33 50 0.83
25 0.42 55 0.92
30 0.50 60 1.00

Common Shifts

Shift Break Paid per day 5 days 6 days
07:00 to 15:30 30 min 8 h 40 h 48 h
07:30 to 17:00 60 min 8 h 30 min 42 h 30 min 51 h
08:00 to 17:00 60 min 8 h 40 h 48 h
06:00 to 18:00 60 min 11 h 55 h 66 h
22:00 to 06:30 30 min 8 h 40 h 48 h

Frequently Asked Questions

How do I calculate hours worked?

Subtract the start time from the end time, then take off unpaid breaks. 07:30 to 16:00 is 8 h 30 min; less a 30-minute lunch, that is 8 h paid.

How do I convert minutes to decimal hours?

Divide the minutes by 60. 15 min = 0.25 h, 30 min = 0.5 h and 45 min = 0.75 h, so 7 h 45 min is 7.75 h on a timesheet.

How do I work out hours for a night shift?

When the end time is earlier than the start, the shift runs past midnight: add 24 hours to the end time. 22:00 to 06:30 is 30:30 − 22:00 = 8 h 30 min; less a 30-minute break, 8 h.

How do I add hours and minutes?

Add the hours and the minutes separately, then carry every 60 minutes into an hour. 3 h 45 min + 2 h 30 min = 5 h 75 min = 6 h 15 min.

How many hours is 7 a.m. to 3:30 p.m.?

8 hours 30 minutes. With a 30-minute unpaid break, 8 paid hours a day, or 40 hours over a five-day week.

How do I find what time a job will finish?

Add the duration to the start time. A concrete pour starting at 07:00 that takes 5 h 30 min finishes at 12:30. Past 24:00, take off 24 hours and it finishes the next day.