CONCRETE · FIELD TOOL

Concrete Truck Calculator

Trucks needed = pour volume (with wastage) ÷ truck capacity, rounded up. A 48 m³ slab with 5% wastage is about 50.5 m³, so with 8 m³ trucks you need 7 truck loads: 6 full trucks and a last truck carrying 2.5 m³.

Inputs

Results update as you type.

Quick Start
Pour
m
m
mm
%
Trucks
m³
Slab plan and section20 m12 mSection200 mmmyconstructioncalculator.comNot to scale
Diagram updates as you type.

Results

Check the working before you order.

Truck loads
7trucks
Order quantity50.50 m³
Last truck load2.50 m³
Net volume48.00 m³

The last truck carries only 2.50 m³. Many plants charge a short-load fee below about half a load (check before ordering).

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Volume = L × W × T = 20.00 × 12.00 × 0.200 m = 48.00 m³
  2. With 5% wastage: 48.00 × 1.05 = 50.40 m³
  3. Round up to the next 0.5 m³ for ordering: 50.50 m³
  4. Trucks = ⌈50.50 ÷ 8.00⌉ = 7
  5. 6 full loads of 8.00 m³ + last truck with 2.50 m³

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formula

Order volume = Net volume × (1 + wastage % ÷ 100), rounded up to the ordering step
Truck loads  = ⌈ Order volume ÷ Truck capacity ⌉
Last load    = Order volume − (Truck loads − 1) × Truck capacity

⌈ ⌉ means “round up to the next whole number”. You cannot order a fraction of a truck.

Worked Example

A ground slab 20 m long, 12 m wide and 200 mm thick, poured with 8 m³ trucks:

  1. Net volume = 20 × 12 × 0.20 = 48.0 m³
  2. With 5% wastage = 48.0 × 1.05 = 50.4 m³
  3. Round up to the next 0.5 m³ = 50.5 m³ to order
  4. Trucks = ⌈50.5 ÷ 8⌉ = ⌈6.31⌉ = 7 trucks
  5. Six full trucks carry 48 m³; the seventh carries 2.5 m³

That last load is under a third of the drum. Before you place the order, ask the plant whether a short-load charge applies, or whether two 9 m³ trucks at the end would work better.

Trucks Needed by Pour Volume

Order volume already includes wastage. Each figure is rounded up.

Order volume 6 m³ trucks 8 m³ trucks 10 m³ trucks
10 m³ 2 2 1
20 m³ 4 3 2
30 m³ 5 4 3
50 m³ 9 7 5
100 m³ 17 13 10

Planning the Pour on Site

  • Spacing the trucks. Divide your placing rate (pump or crane output, often 20–40 m³/h on a slab) by the truck size to get the arrival interval. At 30 m³/h and 8 m³ trucks, you need a truck about every 16 minutes.
  • Hold the last truck. Ask the plant to batch the final truck only after you call it in, once you can measure the actual remaining volume.
  • Check the volume against the drawings. Slab thickness on site is often more than drawn because of subgrade levels. A 10 mm overrun on a 240 m² slab is another 2.4 m³: a third of a truck.

Assumptions

  • The calculator works with whatever truck capacity you enter. Defaults are 8 m³ (metric) and 10 yd³ (imperial).
  • Orders are rounded up to 0.5 m³ or 0.25 yd³.
  • Volume is for a rectangular pour. For footings, columns and beams, use the concrete volume calculator and enter the total here with “Total volume”.

Frequently Asked Questions

How many cubic metres does a concrete truck hold?

Most ready-mix trucks carry 6 to 10 m³. 8 m³ is a common default in many markets, and 9–10 m³ trucks are used on large pours where roads allow. The legal load depends on axle limits, so ask your batching plant what they will actually send.

How many cubic yards are in a concrete truck?

A typical US mixer truck carries 8 to 11 cubic yards when full, with 10 yd³ a common planning figure. Short-load trucks for small jobs carry less.

Should I round up my concrete order?

Yes. Order the volume with wastage, then round up to the plant's ordering step (usually 0.5 m³ or 0.25 yd³). Running short mid-pour risks a cold joint, which costs far more than a small surplus.

What is a short-load fee?

Many plants charge extra when a truck carries less than about half its capacity, because the truck and driver cost the same either way. If your last truck is nearly empty, check whether adjusting the order or the truck size avoids the fee.

How much wastage should I allow for a concrete pour?

Around 3–5% for suspended slabs on accurate formwork and 5–10% for ground slabs and footings, where uneven subgrade and over-excavation take extra concrete. Pump line priming also uses some concrete.