CONCRETE CURING & POUR PLANNING · FIELD TOOL

Concrete Curing Time Planner

Normal (class N) cement at 20 °C reaches 50% of its 28-day strength in about 2 days, 70% in about 4.8 days and 78% at 7 days. In colder weather it slows: at 10 °C, 70% takes about 7.7 days. ACI 308.1 asks for at least 7 days of curing (3 days for high-early cement).

Inputs

Results update as you type.

Pour
°C
Targets
Strength milestonesStrength milestonescuring 7 days01371428days50%70%100%myconstructioncalculator.com
Diagram updates as you type.

Results

Check the working before you order.

Minimum moist curing (ACI 308.1)
7 days→ Mon, 9 Nov 2026
50% of 28-day strength47 hours → Wed, 4 Nov 2026
70% (soffit striking)4.8 days → Sat, 7 Nov 2026
100% (28-day strength)28.1 days → Mon, 30 Nov 2026
Strength at 7 days78 % of 28-day

Estimates only. Confirm striking times with field-cured cubes or maturity sensors and the engineer’s approval.

Price This optional: add your own prices

Your prices are remembered on this device only.

Send Order WhatsApp, SMS or email to your supplier
Include
Working
  1. Strength gain βcc(t) = exp{s[1 − √(28/t)]}, s = 0.25 for class N (EN 1992-1-1 Eq. 3.2)
  2. Temperature-adjusted age: 0.998 equivalent days per day at 20 °C (Annex B)
  3. Days to ratio r = 28 ÷ (1 − ln r ÷ s)² ÷ temperature factor → 50%: 2.0, 70%: 4.8, 100%: 28.1 days
Site Reminders

Get a notification on this phone on the day. Tick the dates you want, then tap Remind me.

Results are estimates for planning and material ordering only. They are not a substitute for structural design or approval by a qualified engineer. Read the full disclaimer.

Formulas

Strength ratio     βcc(t) = exp{ s × [1 − √(28 ÷ t)] }       s = 0.20 (R), 0.25 (N), 0.38 (S)
Temperature factor  = exp{ −(4000 ÷ (273 + T) − 13.65) }      equivalent days per real day
Days to ratio r     = 28 ÷ (1 − ln r ÷ s)² ÷ temperature factor

Worked Example

Class N cement, average 20 °C, poured Monday 2 November 2026:

  1. 50% strength: 28 ÷ (1 + 0.693/0.25)² ≈ 2.0 days → Wednesday 4 November
  2. 70% (soffit striking): ≈ 4.8 days → Saturday 7 November
  3. ACI 308.1 minimum curing: 7 days → Monday 9 November
  4. At 7 days the concrete is at about 78% of its 28-day strength

Days to Reach 70% of 28-day Strength

Average temperature Class R Class N Class S
5 °C (41 °F) 7.6 10.0 15.6
10 °C (50 °F) 5.9 7.7 12.1
20 °C (68 °F) 3.6 4.8 7.5
30 °C (86 °F) 2.3 3.0 4.8

Frequently Asked Questions

How long does concrete take to cure?

Concrete keeps gaining strength for months, but most specifications require at least 7 days of moist curing for normal cement (3 days for high-early cement, longer for slag or fly ash blends). It reaches about 70% of its 28-day strength in roughly 5 days at 20 °C.

When can formwork be removed?

Side forms are often struck after about 24 hours. Soffits and props need the concrete to reach a strength set by the engineer (often 60–75% of the 28-day strength) which depends heavily on temperature and cement type.

How does temperature affect curing time?

Strength develops more slowly in the cold. Using the EN 1992-1-1 temperature-adjusted age, a day at 10 °C counts as about 0.62 days at 20 °C, and a day at 30 °C as about 1.57 days.

References

  • EN 1992-1-1 Eq. 3.2: βcc(t) = exp{s[1 − (28/t)^½]}; Annex B Eq. B.10 (temperature-adjusted age)
  • ACI 308.1 (Specification for Curing Concrete)